i. This Monthly Environmental
Monitoring and Audit (EM&A) Report is prepared for Contract No. SPW 07/2020
“Environmental Team for Construction of Yuen Long Effluent Polishing Plant
Stage 1”. Drainage Services Department (DSD) has appointed Fugro Technical
Services Limited (FTS) to undertake the Environmental Team services for the
project and implement the EM&A works.
ii. This is the 15th Monthly
EM&A Report for the Contract which summaries findings of the EM&A
programme during the reporting period from 1 June 2022 to 30 June 2022. As
informed by the Contractor, major activities in the reporting month were:
Breaches of Environmental Quality Performance Limits (AL levels)
iii. No Action and
Limit Level exceedance was recorded for air quality monitoring and construction
noise monitoring in the reporting month.
iv. No Action and
Limit Level exceedance was recorded for water quality monitoring in the
reporting month.
v. No Action / Limit exceedance was recorded for noise levels at stations
(NMS1 and NMS2) in close proximity to the two active
ardeid night roosts (ANR1 and ANR2) observed within the Survey Area during the
reporting month.
vi.
Two exceedances in Action Level were recorded for the ecological
monitoring of birds on 13 & 17 June 2022. These include significant
declines in point count method results for the species diversity of all avifauna
species in the community; and species diversity of species of conservation importance only. However, the exceedances were not project-related.
vii. No corrective
actions were required according to the Event and Action Plans for the
Monitoring Parameters.
Land Contamination
viii. Regular site
inspection was carried out to ensure the recommended mitigation measures are
properly implemented. The signed final Contamination Assessment Report (CAR)
for “Main Storeroom & Workshops”, “Mechanical Workshop” and “Waste Storage
Area” were submitted to EPD respectively
on 1st November 2021, 23rd November 2021 and 29th
April 2022. No
contaminated soil and ground water was
found within the Main Storeroom & Workshop, Mechanical Workshop and the
Waste Storage Area, and
no remedial action is required for both locations. Part of the Site
investigation (SI) work within the SAS Thickener House-1 (i.e. ENV-BH16,
ENV-BH17, ENV-BH22 and ENV-BH23) was completed by 16th May 2022. While
the laboratory results of sampling works show that there is no contaminated soil or groundwater within the
SAS Thickener House-1, the findings are summarized in the draft CAR for the
area which is under review and will be submitted to EPD.
Complaint Log
ix. No complaints were
received in the reporting period.
Notifications of Summons and Successful Prosecutions
x. No notifications
of summons and successful prosecutions were received in the reporting period.
Reporting Change
xi. There were no
reporting changes during the reporting month.
Future Key Issues
xii. The main works
will be anticipated in the next three months are as follow:
9. NON-COMPLIANCE,
COMPLAINTS, NOTIFICATIONS OF SUMMONS AND SUCCESSFUL PROSECUTIONS
10. IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURE
Tables
Table 1.1 Contact Information of Key Personnel
Table 1.2 Environmental
Licenses, Notification and Permits Summary
Table 2.1 Air
Quality Monitoring Equipment
Table 2.2 Air
Quality Monitoring Location
Table 2.3 Summary
of Air Quality Monitoring Results
Table 2.4 Comparison of
1-hr TSP data with EIA predictions
Table 3.1 Construction
Noise Monitoring Equipment
Table 3.2 Monitoring
Parameters and Frequencies of Noise Monitoring
Table 3.3 Construction
Noise Monitoring Location
Table 3.4 Summary
of Construction Noise Monitoring Results
Table 3.5 Comparison of
Noise monitoring data with EIA predictions
Table 4.1 Water Quality Monitoring and Sampling
Equipment
Table 4.2 Monitoring Parameters and Frequency
Table 4.3 Coordinates
of Water Quality Monitoring Locations
Table 4.4 Summary of
Water Quality Exceedance
Table 5.1 Noise
Monitoring Parameters (For Active Ardeid Night Roost Survey)
Table 5.2 Active Ardeid
Night Roost Survey Findings
Table 5.3 Noise
Monitoring Results (For Active Ardeid Night Roost Survey)
Table 5.4 Noise
Monitoring Parameters
Table 5.5 Abundance of
all Avifauna Species
Table 5.6 Abundance of
Species of Conservation Importance
Table 5.7 Shannon Diversity
Index Value of all Avifauna Species
Table 5.8 Shannon
Diversity Index Value of Species with Conservation Importance
Table 5.9 Wetland
habitat utilization of all avifauna species
Table 5.10 Wetland
habitat utilization of avifauna species of conservation importance
Table 5.11 Noise Monitoring Results (For
Ecological Monitoring of Birds)
Table 8.1 – Waste
Generated by the Construction and Disposal Ground
Table 10.1 – Status of submissions required under
the EP
Figures
Figure 1 Location of Proposed Yuen Long Effluent Polishing Plant
Figure
2 Location of Construction Dust Monitoring Stations
Figure
3 Noise Monitoring Locations
Appendices
Appendix A Construction
Programme
Appendix B Project Organization Chart
Appendix C Action and Limit Levels
Appendix D Calibration Certificates/ Reports of Monitoring Equipments
Appendix E Environmental Monitoring Schedule
Appendix F Environmental Monitoring Results
Appendix H Event and Action Plan
Appendix J Implementation Status of Environmental Mitigation Measures
Appendix K Weather and Meteorological Conditions
Appendix M Summary of the ET Leader’s Site Environmental Audit in the
Reporting Month
Appendix N Outstanding Issues and Deficiencies
Appendix O Active Night Roost Monitoring Area and Vantage Points; and Noise Monitoring
Stations
Appendix P Ecological Bird Monitoring Area with Locations of Point Count
Sites and Transect Route